子公司润邦海洋成功交付澳大利亚KMSB Floating Pontoon & Jacket & Linkspan项目

360影视 动漫周边 2025-05-16 09:59 2

摘要:近日,子公司润邦海洋为澳大利亚TAMS集团建造的1座浮码头, 3套导管架和1套栈桥项目已圆满交付并通过半潜船和重吊船运输启航至澳大利亚。项目的顺利交付是润邦海洋布局国际化战略、深耕澳大利亚市场的里程碑,标志着润邦海洋高端海洋工程装备建造实力再次获得海外客户的高

完美履约

近日,子公司润邦海洋为澳大利亚TAMS集团建造的1座浮码头, 3套导管架和1套栈桥项目已圆满交付并通过半潜船和重吊船运输启航至澳大利亚。项目的顺利交付是润邦海洋布局国际化战略、深耕澳大利亚市场的里程碑,标志着润邦海洋高端海洋工程装备建造实力再次获得海外客户的高度认可。

项目总重量约13,000吨,材料最高等级为1100Mpa, 其中460C等级材料近2,500吨,采用DNV和AS标准建造,按照100% NDT要求进行检验。自去年承接项目以来,润邦海洋项目组全力以赴,建造过程中,项目团队攻克了高强度等级材料焊接、抱环闭合试验、海生物水下清理、甲板面大面积防滑砂施工、Dolphin高精度吊装试验等难题。润邦海洋充分发挥自身的技术优势,不断地探索和创新,利用模块车进行船台搭载等新工艺,大幅缩短建造工期,降低作业风险,确保项目按计划顺利推进,最终提前近2个月高质量交付,高强度材料焊接UT合格率达到99.86%。

该项目将应用于KMSB码头,用于停靠大型浮式生产储卸油船(FPSO)、汽车滚装船等大型船只,提高码头装卸效率、推动区域经济繁荣。客户多次表示润邦海洋展现的专业技能和完美履约精神令人印象深刻,为双方未来长期合作奠定了坚实的基础。

此次项目积累的宝贵技术经验将应用于后续项目中,润邦海洋也将持续聚焦高端海洋工程装备,为全球客户提供更优质的海工装备解决方案。

Recently, ROC has successfully delivered a project consisting of 1 floating pontoon, 3 jackets and 1 linkspan built for TAMS Group in Australia. The project was shipped to Australia via semi - submersible vessel and heavy - lift vessel. The smooth delivery of this project is a milestone in the company's international strategic layout and its deep - rooted development in the Australian market. It marks that the company's high - end marine engineering equipment construction strength has once again been highly recognized by overseas customers.

The total weight of the project is approximately 13,000 tons, with the highest material grade reaching 1100 Mpa, and nearly 2,500 tons of 460C - grade materials. The project was constructed in accordance with DNV and AS standards and inspected in line with 100% NDT requirements. Since undertaking the project last year, the project team of ROC has gone all out. During the construction process, the project team overcame numerous challenges, such as welding of high - strength - grade materials, closure tests of pile guides, underwater cleaning of marine organisms, large - area anti - slip sand construction on deck surfaces, and high - precision hoisting tests of dolphins. ROC gave full play to its technical advantages, continuously explored and innovated. New processes like using modular vehicles for ship - building berth installation were adopted, which significantly shortened the construction period, reduced operation risks, ensured the smooth progress of the project as planned. Eventually, the project was delivered with high quality nearly 2 months ahead of schedule, and the ultrasonic testing (UT) qualification rate of high - strength material welding reached 99.86%.

This project will be applied at KMSB Wharf, used for berthing large - scale Floating Production Storage and Offloading vessels (FPSOs), ro - ro car carriers and other large ships. It will help improve the wharf handling efficiency and promote regional economic prosperity. The customer has repeatedly stated that the professional skills and perfect performance spirit demonstrated by ROC are impressive, laying a solid foundation for the long - term cooperation between the both parties in the future.

The valuable technical experience accumulated from this project will be applied to subsequent projects. ROC will also continue to focus on high - end marine engineering equipment and provide better marine engineering equipment solutions for global customers.